Site Map Sent Mail
 
INSTITUTIONAL
Directorate
Erol ADIGÜZEL / Engineer
03/06/1942

Academic and Professional Attainment
Fachhochschule Bielefeld 1968 Germany Diplom Ingenieur
Technical High School 1963 Eskişehir
Summary of Experience
28 years Construction of Marine Structures and Tunnels
5 years Design and Construction of Infrastructures
1 years Construction of Roads and Dams

Resident Foreign Experience

6 years Germany
6 years S.Arabia
2 years Pakistan

Language
German
English

WORK EXPERIENCE

1996
2ER Construction Industry Foreign Trade Co. - President

CEI Consultant Engineers International (BVI) Ltd.- Partner
“Tunnels and Underground Works” - “Management Advisor”
S.S Arıköy Dwelling House Project
“General Coordinator”
BUTANGAZ Thrace LPG Terminal Project
“Consultant/Project Coordinator”
ERCAN CANMUTLU Shopping Center
“Project Coordinator”
ALARKO-ALSİM Contracting Group
Tender Department Road and Tunnel
“Consultant/Expert Eng.”
Republic of Kazakhstan, Ministry of Transport and Communications.
Western-North Kazakhistan Road Network Rehabilitation Projects
ALARKO-ALSİM Contracting Group Tender Department
Consultant /Expert Engineer
İstanbul-Marmaray Project
Ankara-Eskişehir TCDD Railway Tunnels Project
Eskişehir-Adapazarı TCDD Railway Tunnels Project
İstanbul-Bosphorus Crossing Tunnel
ZUBLIN & LIMAK Co.
1994 – 1995
STFA Construction Co. – Deputy General Manager

Road & Dam Works
Responsible for coordination and follow up all technical and constructional
aspects related with onshore projects such as roads and dams
constructions, and tendering for new projects.
- Construction of Lahore By-Pass Lahore-Pakistan
- Shorinullah-Rajanpur Highway Construction Karachi-Pakistan
- Saraigambila-Karak Highway Construction Islamabad-Pakistan
- Sazlıdere Dam Construction Istanbul-Turkey
1987 – 1994
STFA Construction Co. – Deputy General Manager

Tunnels and Underground Works
Responsible for coordination and follow up all technical and constructional
aspects related with onshore projects such as roads and dams
constructions, and tendering for new projects.
Istanbul Sewerage Project Kabataş-Baltalimanı Tunnel
ISkenderun-Divriği Railway Electrification
First Stage of Istanbul Sewerage Project,
Construction of North Golden Horn Collectors
1985 – 1987
STFA Construction Co. – Project Manager

South Haliç Sewerage Tunnels Project – Istanbul
The project comprises boring of 3 tunnels on the South West side of Golden
Horn, 1865 m, 2463 m and 2046 m long respectively, construction of
21 manhole chambers, 975 m R.C. pipe installations in open cut trenches
and sea outlet structures.
1984 – 1985
STFA Construction Co. – Project Manager

Tohma and Kömürhan Highway Bridges Project - Malatya
The project involves the construction of the 287 m long Kömürhan Highway
bridge across the Euphrates river between Malatya and Elazığ and the
517,5 m long Tohma combined highway railway bridge across the Tohma
river between Malatya and Elazığ. The bridges will across the future
reservoir of the Karakaya dam now under construction. The construction of
these two bridges also includes as well drainage paving, curbs, handrails
and other sundry works
1979 – 1984
STFA Construction Co. – Project Manager

Muna Tunnels Project – Makkah, S.Arabia
The project is the construction of the first three toilet tunnels of the Muna
project, facing Kaabe to provide toilet facilities to 600 pilgrims
simultaneously, especially during the Hadj Season, and also the
construction of two parallel vehicular tunnels, as part of the transportation
system to facilitate the vehicular pilgrimage traffic between Kaabe and Holy
Places during Hadj Season in Makkah
1976 – 1979
STFA Construction Co. – Project Manager

Çanakkale Cement Factory Harbour – Çanakkale
Responsible for execution of construction works of Harbour of Cement
Factory which involves the construction of 200 meter long concrete block
quay and a piled jetty to accommodate 30.000 DWT vessels and ferry boats
including loading and unloading installations
1972 – 1976
STFA Construction Co. – Assistant Project Manager

Yeşilköy Airport Maintenance Buildings
Responsible for the construction of airport maintenance complex which
comprises of a hangar building, an engine test building, a ground equipment
and vehicle shop, a catering building and a power station building.
1968 – 1970
Integral Architekten und Ingenieure GmbH

Düsseldorf/GERMANY
Shift Design Engineer and Consulting Engineer
- Iron Casting Factory
- Dunlop Tire Factory
- Ford Shaft Factory
- Ford Car Factory