MARPORT MAIN CONTAINER TERMINAL MODIFICATION AND EXPANSION PROJECT

MARPORT MAIN CONTAINER TERMINAL MODIFICATION AND EXPANSION PROJECT

Ambarlı Port is situated in Yakuplu Village at Angurya farm area.

In 2001, Arkas Holding Group commissioned 2ER-CEI both for the assessment of existing situations of the superstructure and infrastructure systems of KUMPORT and ARMAPORT Wharfs, which are located in the Ambarlı Port Complex, in terms of static-steel and reinforced concrete, and for preparation and modification of the projects according to new load and calculation of the costs on the basis of budget, if necessary.

Within this context, the following works were carried out:

  • Bathymetric maps of the jetties were developed
  • Land/Sea drilling for the evaluation of carrying capacity of soil and to decide the dredging equipment
  • Concrete Samples from existing structures for testing chlorination and carbonation
  • Determination of Corrosive effects of the sea water on the pile wall thickness
  • Modification Drawings of the jetties in line with the load requirements of SSG Cranes
  • Bill of quantity preparation for Budgetary purposes

Following the completion of these studies and the submission of an advisory report, the decision to acquire ARMAPORT was concluded.

ARMAPORT Container Terminal Consultancy/Control Engineering Services

ARKAS Holding CO. Commissioned 2ER-CEI to carry out the Consultancy/Control Engineering Services for the extension and modification of the Armaport into a Container Terminal, within this context, Engineering, Consultancy, Contol Engineering Services were carried out for the following works:

  • Modification of the existing A1 and A2 jetties in line with the new Post Panamax Cranes and new earthquake regulations; joining of the pile driven supported beam Rails constructed recently to the existing structure with a chemical anchorages,
  • Joining of the existing A1 and A2 jetties on their outer ends by means of pile driven Jetty namely A5
  • Sea and Land filling up of the closed Area between A1, A2 and A5 jetties from a Mol for Container Stock Yard,
  • Construction of infrastructure systems (Waste Water, Rain Water, Fire Water, Potable Water and Electricity Services) for container stock yards and existing container stock area
  • Paving Works

Construction works are currently continuing and are due for completion in the first half of the year 2004.

Replica Handbags Bottega Veneta imitacion Bvlgari imitacion Celine imitacion Christian Dior imitacion Gucci imitacion Gucci Bag imitacion Gucci Wallet imitacion Gucci Shoes imitacion Gucci Belt imitacion Hermes imitacion Loewe imitacion Louis Vuitton imitacion Louis Vuitton Belt imitacion Louis Vuitton Calf Leather imitacion Louis Vuitton Damier Azur Canvas imitacion Louis Vuitton Damier Ebene Canvas imitacion Louis Vuitton Damier Graphite Canvas imitacion Louis Vuitton Damier Infini Leather imitacion Louis Vuitton Damier Quilt lamb imitacion Louis Vuitton Embossed Calfskin imitacion Louis Vuitton Epi imitacion Louis Vuitton Game On Monogram Canvas imitacion Louis Vuitton Jewellery imitacion Louis Vuitton Key Holder imitacion Louis Vuitton Mahina Leather imitacion Louis Vuitton Monogram Canvas imitacion Louis Vuitton Monogram Denim imitacion Louis Vuitton Monogram Eclipse Canvas imitacion Louis Vuitton Monogram Empreinte imitacion Louis Vuitton Monogram Seal imitacion Louis Vuitton Monogram Shadow imitacion Louis Vuitton Monogram Vernis imitacion Louis Vuitton Monogram Watercolor imitacion Louis Vuitton New Wave imitacion Louis Vuitton Shoes imitacion Louis Vuitton Since 1854 imitacion Louis Vuitton Strap imitacion Louis Vuitton Taiga Leahter imitacion Louis Vuitton Taurillon leather imitacion Louis Vuitton Transformed Game On canvas imitacion Louis Vuitton Utah Calfskin imitacion Louis Vuitton X Supreme imitacion Mulberry imitacion Prada imitacion YSL imitacion