PETKIM CONTAINER TERMINAL PROJECT
Dredging Works
• For Phase 1 (593.925 m3) and for Phase 2 (692.750 m3)
• Backyard and Breakwater Construction Works
• Excavation: For Phase 1 (2.696.110 m3) and for Phase 2 (2.118.837 m3)
• Backfilling: For Phase 1 (936.922 m3) and for Phase 2 (103.366 m3)
• Breakwater is about approximately 300 meters. Rock quantity is 2.645.463 tons
• Concrete Pavement : For Phase 1 (192.053 m2) and for Phase 2 (132.275 m2)
• Water Tank Construction: 664 m3 including for fire.
• Transformer Building Construction.
• Open Pile Quay, Dolphin and Headwall Works
• Purchasing Spiral Steel Pipes Piles: For Phase 1 (12.278 m) and for Phase 2 (9.678 m)
• Purchasing Fenders : For Phase 1 (29 Nos) and for Phase 2 (28 Nos)
• Purchasing Bollards : For Phase 1 (30 Nos) and for Phase 2 (28 Nos)
• Purchasing A 120 Type Rails and its accessories: 700 m for each Phase.
• HV/LV Electrical and Site Lightning Works
Building Works;
• Administration Building,
• Workshop Building,
• Entry Building,
• In Gate Canopy,
• Out Gate Canopy.
•Supply of Electricity Power for Container Terminal Project: 17.9 MVA for both Phase.